Hospital Expansion and Renovation Project

Learn the details of the Hospital Expansion and Renovation Project at Citizens Memorial Hospital in Bolivar, Missouri. The expansion is set to open in 2026.

In the video, CEO/Executive Director Michael Calhoun explains why the hospital is undertaking the $100 million project.

Follow Construction Progress

Why CMH is Expanding the Hospital video with play button

The Campaign for Citizens Memorial Hospital

Impact, inspire and invest in CMH's enhanced patient experience with a gift to The Campaign for Citizens Memorial Hospital. Learn more about the campaign objectives and naming and sponsorship opportunities.

Campaign Details

impact-inspire-invest.webp

Project Details

  • Expansion Size: 117,000-square-feet (3 floors)
  • Remodel Size: 25,000-square-feet
  • Construction Manager: JE Dunn
  • Architect: HMN Architects
  • Cost: $100 million project; $84 million construction cost

Patient Areas

  • New and Expanded Emergency Department
  • New and Expanded Intensive Care Unit
  • New Private Medical/Surgical Unit Rooms
  • New Progressive Care Rooms
  • New Birth Place

Other Features

  • New Hospital Entrance
  • New and Expanded Gift Shop
  • New Kitchen, Cafeteria and Dining Area
  • New Pharmacy
  • Additional Space for Future Growth

Remodel

  • Surgical Department Renovations and Expansion
  • 2 New Cardiac Cath Lab Procedure Rooms

Interior Drawings

Fun Facts

Here are some fun facts to give you a sense of the scale of the project.

Updated February 2026

person icon

The Human Effort

  • 353,000+ hours worked, equal to 403 years
  • 30+ trade partners
  • 920+ workers on site

foundation icon

The Foundations

  • 168 drilled piers, 4,335 ft deep combined. Nearly seven times the height of the St. Louis Arch.
  • 640 tons of reinforced steel in the concrete. Roughly the weight of three Statues of Liberty.
  • 8,444 cu yd, or 33.77 million lbs, of concrete. Enough to fill a football field, including the end zones, nearly 4 ft thick.
  • 953 concrete truck deliveries covering 4,955 miles, equal to driving from Miami, Florida, to Anchorage, Alaska.

brick icon

The Exterior Shell

  • 30,000 concrete blocks
  • 80,000 bricks
  • 27,000 sq ft exterior glass
  • 25,512 sq ft exterior sheathing

paint can and paint brush icon

The Interior Build-Out

  • 800,470 fasteners (screws, pins, etc.)
  • 210,420 sq ft batt insulation
  • 25,526 framing clips
  • 255,027 lin ft of interior framing
  • 64,562 lin ft exterior framing
  • 379,594 sq ft of drywall

cable spool icon

The Hidden Infrastructure

  • 125,644 lbs of sheet metal for the ductwork
  • 300,000 lin ft of low-voltage cabling

Groundbreaking Ceremony

CMH held a groundbreaking ceremony for the hospital expansion on Sept. 28, 2023 — 41 years after the hospital opened on Sept. 28, 1982. Dignitaries, hospital leaders and community members celebrated the upcoming hospital expansion with a ceremonial dirt turning on the construction site.